A project manager is leading a program execution and has challenges, because a project team waits for every decision to be made by the project manager. The progress of the team is slow because the project manager is the bottleneck. Upon assessing the situation, the project manager realized that the team members can handle the work on their own. What should the project manager do?

QuestionsCategory: PMPA project manager is leading a program execution and has challenges, because a project team waits for every decision to be made by the project manager. The progress of the team is slow because the project manager is the bottleneck. Upon assessing the situation, the project manager realized that the team members can handle the work on their own. What should the project manager do?
Admin Staff asked 1 year ago
A project manager is leading a program execution and has challenges, because a project team waits for every decision to be made by the project manager. The progress of the team is slow because the project manager is the bottleneck. Upon assessing the situation, the project manager realized that the team members can handle the work on their own.
What should the project manager do?

A. Raise a resource request to get complimentary training for the project manager and team members.

B. Escalate the situation to the resource manager to ensure the team makes their own decisions.

C. Gather feedback from all team members and define a process to handle the team requests.

D. Revise the roles and responsibilities and empower the team to make their own decisions.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.