A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the purchase of services are taking too long, as the purchasing department has other priorities. What should the project manager do?

QuestionsCategory: PMPA project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the purchase of services are taking too long, as the purchasing department has other priorities. What should the project manager do?
Admin Staff asked 1 year ago
A project manager is leading a project in an organization that has a functional structure. The project manager has been informed by the team that the tasks related to the purchase of services are taking too long, as the purchasing department has other priorities.
What should the project manager do?

A. Ask the project team to keep developing other tasks that do not depend on the purchase of services.

B. Meet with the purchasing manager to find the source of the delays and agree on a purchasing schedule.

C. Request that the purchasing tasks be outsourced through an existing purchasing vendor.

D. Modify the project schedule to accommodate the delays in the purchase of services.










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.