A project manager is leading a project that is in the execution phase. Due to a company reorganization, some key project team members are likely to leave the project. What should the project manager do next?

QuestionsCategory: PMPA project manager is leading a project that is in the execution phase. Due to a company reorganization, some key project team members are likely to leave the project. What should the project manager do next?
Admin Staff asked 1 year ago
A project manager is leading a project that is in the execution phase. Due to a company reorganization, some key project team members are likely to leave the project.
What should the project manager do next?

A. Discuss this issue with the affected team members and support them during the transition.

B. Start looking for replacements as soon as possible to help prevent any schedule slippage.

C. Engage with the project sponsor to ensure that this change does not affect the project execution.

D. Determine the impact to the project and implement mitigations per the project management plan.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.