A project manager is leading a small project with a low budget and a short, tight schedule. Many of the stakeholders are within the organization and have varying levels of interest. Which approach should the project manager use with the stakeholders?

QuestionsCategory: PMPA project manager is leading a small project with a low budget and a short, tight schedule. Many of the stakeholders are within the organization and have varying levels of interest. Which approach should the project manager use with the stakeholders?
Admin Staff asked 1 year ago
A project manager is leading a small project with a low budget and a short, tight schedule. Many of the stakeholders are within the organization and have varying levels of interest.
Which approach should the project manager use with the stakeholders?

A. Provide daily reports to maximize stakeholder communication.

B. Minimize communication until project completion as it will be nished quickly.

C. Share all relevant project information with the stakeholders.

D. Schedule one-on-one meetings with stakeholders to provide project updates.










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.