A project manager is leading an electrical project that spans five towns. The project manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project. What should the project manager do?

QuestionsCategory: PMPA project manager is leading an electrical project that spans five towns. The project manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project. What should the project manager do?
Admin Staff asked 1 year ago
A project manager is leading an electrical project that spans five towns. The project manager is informed by the team that one of the towns is not allowing the team to work there even though the town was included in stakeholder engagements before the start of the project.
What should the project manager do?

A. Engage with the town's authorities to discuss the reason for the change in commitment and agree on a solution.

B. Instruct the team to move to the next town and continue the project to avoid further delays.

C. Change the project scope and seek approval to exclude this town from the overall project.

D. Retrieve all minutes of stakeholder engagements and send to the town as a reminder of their commitment to the project.










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.