A project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently. How should the project manager respond?

QuestionsCategory: PMPA project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently. How should the project manager respond?
Admin Staff asked 1 year ago
A project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently.
How should the project manager respond?

A. Record the issue in the issue log and escalate the con ict to the project sponsor for assistance.

B. Explain to the stakeholder that the stakeholder engagement plan requires their attendance at all reviews.

C. Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework.

D. Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to re ect this reduced attendance.










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.