A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts. However, a few stakeholders are reporting that they are unable to find the latest project schedule. What should the project manager do?

QuestionsCategory: PMPA project manager is managing a hybrid project. There is software in place to access the repository of project artifacts. However, a few stakeholders are reporting that they are unable to find the latest project schedule. What should the project manager do?
Admin Staff asked 1 year ago
A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts. However, a few stakeholders are reporting that they are unable to find the latest project schedule.
What should the project manager do?

A. Advise the project management office (PMO) that there is a resource gap for sharing project artifacts effectively.

B. Make sure all stakeholders have access to the system and know where to find project artifacts.

C. Escalate the issue to the steering committee and ask them to deal with the stakeholders' lack of training.

D. Send the project schedule via email to the stakeholders who need that information.










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.