A project manager is managing a new type of project for a traditional organization. The culture of the organization is not typically in support of change. Which two factors should the project manager consider in developing the portion of the project plan related to culture? (Choose two.) A. The relevant experience and quali cations of each team member. B. The amount of exibility the team exercises while doing work. C. The amount of risk the organization is willing to accept. D. The speed the team can perform without compromising quality. E. The in uence of the stakeholders on the project. Correct Answer: CE This question is in PMP exam For getting PMP Certificate