A project manager is managing the transition to operations. The project sponsor wants to ensure that good support is provided to the end users. What should the project manager do? A. Ensure that comprehensive documentation is handed over. B. Ask the project team to provide operational support for 1 year. C. Ensure that knowledge is transferred to the operations team. D. Ensure that the user guide is detailed and has clear instructions. Correct Answer: C This question is in PMP exam For getting PMP Certificate