A project manager is newly assigned to the second phase of an ongoing project. During the implementation, a defect occurred and no one knows how to fix it, as the former engineering team has moved to another project. The customer warns that previously. this defect negatively affected the project schedule. What should the project manager do first?

QuestionsCategory: PMPA project manager is newly assigned to the second phase of an ongoing project. During the implementation, a defect occurred and no one knows how to fix it, as the former engineering team has moved to another project. The customer warns that previously. this defect negatively affected the project schedule. What should the project manager do first?
Admin Staff asked 1 year ago
A project manager is newly assigned to the second phase of an ongoing project. During the implementation, a defect occurred and no one knows how to fix it, as the former engineering team has moved to another project. The customer warns that previously. this defect negatively affected the project schedule.
What should the project manager do first?

A. Check the organizational process assets (OPAs).

B. Update the risk management plan.

C. Acquire knowledgeable resources.

D. Extend the timeline of the project.










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.