A project manager is part of a global project team and is in charge of managing the scope defined by their country. There is a clear division regarding which pieces of the scope should be treated by global and local teams. During the last sprints, the project manager has been receiving requests that the global team should handle. What should the project manager do in this situation? A. Assess the team's capacity to absorb the workload B. Evaluate and understand the cause of the con ict C. Escalate the situation to the project sponsor D. Reject the workload back to the global team Correct Answer: B This question is in PMP exam For getting PMP Certificate