A project manager is performing the role of scrum master for a team of developers. There is a con ict among the developers, generated by differences in how a feature can be delivered. The project manager organized a few spikes to resolve this con ict. What should the project manager do next?

QuestionsCategory: PMPA project manager is performing the role of scrum master for a team of developers. There is a con ict among the developers, generated by differences in how a feature can be delivered. The project manager organized a few spikes to resolve this con ict. What should the project manager do next?
Admin Staff asked 1 year ago
A project manager is performing the role of scrum master for a team of developers. There is a con ict among the developers, generated by differences in how a feature can be delivered. The project manager organized a few spikes to resolve this con ict.
What should the project manager do next?

A. Organize a multivoting event to achieve consensus of the whole team.

B. Allow the team to decide on their own which option should be implemented.

C. Organize more spike events until consensus of the team is reached.

D. Ask the project sponsor to decide which option should be implemented.










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.