A project manager is transitioning from a predictive life cycle project to a new agile project. How should the project manager manage and control the scope for the new project? A. Estimate the work the team can complete and define story sizes to keep the project under control B. Spend a short amount of time de ning the scope and building prototypes to re ne the requirements C. Develop a plan to complete more work in less time D. Create a scope baseline and put the rest as backlog activities Correct Answer: A This question is in PMP exam For getting PMP Certificate