A project manager is transitioning from a predictive life cycle project to a new agile project. How should the project manager manage and control the scope for the new project?

QuestionsCategory: PMPA project manager is transitioning from a predictive life cycle project to a new agile project. How should the project manager manage and control the scope for the new project?
Admin Staff asked 1 year ago
A project manager is transitioning from a predictive life cycle project to a new agile project. How should the project manager manage and control the scope for the new project?

A. Estimate the work the team can complete and define story sizes to keep the project under control

B. Spend a short amount of time de ning the scope and building prototypes to re ne the requirements

C. Develop a plan to complete more work in less time

D. Create a scope baseline and put the rest as backlog activities










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.