A project manager is using an agile approach. During the sprint planning meeting, the product owner agged a backlog item as high business value and easy to implement. However, the other team members identified a high dependency between this item and another item that is agged as low business value and high complexity. What should the project manager do to support the backlog prioritization? A. Support the team to move both items to the next sprint when the team will know more. B. Prioritize the item agged as high business value and low complexity for this sprint. C. Facilitate the discussion until the team reaches an agreement about the two items. D. Prioritize the item agged as a dependency with low business value and high complexity. Correct Answer: C This question is in PMP exam For getting PMP Certificate