A project manager is working on a major construction project. Part of the agreed-upon plan was to use a cloud-based system with a server that runs on high- speed internet service since most of the team members work virtually. The company needs to reduce operating costs as much as possible and management insists that the project will now use a system running on a conventional dial-up service. What should the project manager do next? A. Agree with management and continue working the project management plan. B. Evaluate the impact of this decision and communicate with management. C. Replace some of the team members that work virtually to help the company save money. D. Meet with management about their decision and ask them to get another project manager. Correct Answer: B This question is in PMP exam For getting PMP Certificate
Please login or Register to submit your answer