A project manager is working on a software development contract. The project is halfway through a 3-year contract when there is a change in the political landscape and 20% of the stakeholders are replaced. Almost immediately decisions become delayed, invoices go unpaid, and meetings become unmanageable. What tool would assist the project manager to better understand the new project landscape?

QuestionsCategory: PMPA project manager is working on a software development contract. The project is halfway through a 3-year contract when there is a change in the political landscape and 20% of the stakeholders are replaced. Almost immediately decisions become delayed, invoices go unpaid, and meetings become unmanageable. What tool would assist the project manager to better understand the new project landscape?
Admin Staff asked 1 year ago
A project manager is working on a software development contract. The project is halfway through a 3-year contract when there is a change in the political landscape and 20% of the stakeholders are replaced. Almost immediately decisions become delayed, invoices go unpaid, and meetings become unmanageable.
What tool would assist the project manager to better understand the new project landscape?

A. Communication analysis

B. Power distance analysis

C. Stakeholder analysis

D. Engagement analysis










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.