A project manager is working on an agile project. The organization decided to implement the Scrum framework. The project manager organized a workshop to explain the differences between traditional project artifacts and the Scrum approach. The most frequent question raised is what artifact will replace the project schedule. What should be the project manager's response? A. Product roadmap and sprint backlog B. Sprint backlog and scrum board C. Sprint plan and product roadmap D. Product backlog and scrum board Correct Answer: D This question is in PMP exam For getting PMP Certificate