QuestionsCategory: PMPA project manager is working with a co-located agile project team that has worked together long enough to be in the performing phase of team development. An unforeseen event has caused the team to be dispersed and they are now unable to co-locate. What should the project manager do to keep the team performing as effectively as possible?
Admin Staff asked 1 year ago
A project manager is working with a co-located agile project team that has worked together long enough to be in the performing phase of team development. An unforeseen event has caused the team to be dispersed and they are now unable to co-locate. What should the project manager do to keep the team performing as effectively as possible?

A. Ask the project sponsor and executive stakeholders to encourage the team to maintain their performance

B. Provide the team with virtual collaboration software and training on the software to minimize disruption

C. Transition the team from an agile approach to a predictive approach for better performance control

D. Evaluate project performance and step in if performance decreases to an unacceptable level










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.