A project manager led the implementation of an electronic invoicing project that has just been completed. The financial manager communicated that the team discovered three invoices with errors. Which two documents should the project manager update as soon as possible? (Choose two.) A. Issue log B. Risk register C. Stakeholder register D. Change log E. Backlog register Correct Answer: AB This question is in PMP exam For getting PMP Certificate