A project manager meets with the development team to estimate the time required to complete a software application. The software developers are new to the company, and they have never developed a similar application. Which estimation technique should the project manager recommend? A. Analogous estimating B. Parametric estimating C. Planning poker D. Three-point estimating Correct Answer: D This question is in PMP exam For getting PMP Certificate