A project manager notices the team is disagreeing on the level of effort required to complete a task. What should the project manager do?

QuestionsCategory: PMPA project manager notices the team is disagreeing on the level of effort required to complete a task. What should the project manager do?
Admin Staff asked 1 year ago
A project manager notices the team is disagreeing on the level of effort required to complete a task. What should the project manager do?

A. Advise the team that an average of all the estimates will be used as it will be the most reliable level of effort.

B. Advise the team that they can resolve the estimation issue and they can work on it as long as it takes.

C. Advise each team member to explain the rationale for their estimate and then ask the team to come to consensus.

D. Advise the team that the project manager will determine the level of effort since the team cannot agree.










Correct Answer: C

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.