A project manager notices the team is disagreeing on the level of effort required to complete a task. What should the project manager do? A. Advise the team that an average of all the estimates will be used as it will be the most reliable level of effort. B. Advise the team that they can resolve the estimation issue and they can work on it as long as it takes. C. Advise each team member to explain the rationale for their estimate and then ask the team to come to consensus. D. Advise the team that the project manager will determine the level of effort since the team cannot agree. Correct Answer: C This question is in PMP exam For getting PMP Certificate
Please login or Register to submit your answer