A project manager prepared a project benefits management plan. Which of the following should be included in this document?

QuestionsCategory: PMPA project manager prepared a project benefits management plan. Which of the following should be included in this document?
Admin Staff asked 1 year ago
A project manager prepared a project benefits management plan.
Which of the following should be included in this document?

A. Strategic alignment, benefits owner, risk register

B. Target benefits, benefits owner, lessons learned

C. Project requirements, target benefits, issue log, metrics

D. Target benefits, strategic alignment, time frame for realizing benefits










Correct Answer: D

This question is in PMP exam