A project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project and the customer. What should the project manager do?

QuestionsCategory: PMPA project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project and the customer. What should the project manager do?
Admin Staff asked 1 year ago
A project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project and the customer.
What should the project manager do?

A. Reject the suggestion and ask the team member to focus on executing the plan

B. Ask the team member to submit a formal change request

C. Accept the suggestion as it has no impact on the project

D. Ask another team member to validate the impacts of the suggestion










Correct Answer: B

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.