A project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project and the customer. What should the project manager do? A. Reject the suggestion and ask the team member to focus on executing the plan B. Ask the team member to submit a formal change request C. Accept the suggestion as it has no impact on the project D. Ask another team member to validate the impacts of the suggestion Correct Answer: B This question is in PMP exam For getting PMP Certificate