A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, but management wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach. Most of the team members complained about changing approaches because the performance of this team has always been above average among the IT teams in the bank. Which two actions should the project manager take? (Choose two)

QuestionsCategory: PMPA project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, but management wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach. Most of the team members complained about changing approaches because the performance of this team has always been above average among the IT teams in the bank. Which two actions should the project manager take? (Choose two)
Admin Staff asked 1 year ago
A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, but management wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach. Most of the team members complained about changing approaches because the performance of this team has always been above average among the IT teams in the bank.
Which two actions should the project manager take? (Choose two)

A. Interview the most resistant team members to persuade them to try to accept an agile approach.

B. Conduct training sessions with the team so that the team can understand what the agile approach and mindset are.

C. Brainstorm with the team to understand the specifics of the team's project and to identity possible alternative approaches for the team.

D. Ask the team to identify the product backlog and create a kanban board for the team to manage and follow the approach.

E. Meet with management to explain the team's resistance to the agile approach and request that they formally ask the team to implement agile.








Correct Answer: BC

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.