A project manager was recently assigned to rescue a high-priority project for an Olympic facility. The project is behind schedule. with a heavy contractual penalty. The former project manager had numerous con icts with the project team members and a few stakeholders. What should the project manager do first?

QuestionsCategory: PMPA project manager was recently assigned to rescue a high-priority project for an Olympic facility. The project is behind schedule. with a heavy contractual penalty. The former project manager had numerous con icts with the project team members and a few stakeholders. What should the project manager do first?
Admin Staff asked 1 year ago
A project manager was recently assigned to rescue a high-priority project for an Olympic facility. The project is behind schedule. with a heavy contractual penalty. The former project manager had numerous con icts with the project team members and a few stakeholders.
What should the project manager do first?

A. Review the lessons learned register with the former project manager in a private meeting.

B. Meet the project team to assert authority and reassign the project tasks for a timely delivery.

C. Review the project schedule and ask for the contingency reserve to crash the project.

D. Meet the project team and stakeholders to identify the root cause of the issue and develop a solution.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.