A project manager who is managing a critical project in a multinational company is conducting a progress meeting with all team members. During the meeting, one of the team members states that they are facing a critical problem that will prevent them from completing their assigned task. What should the project manager do? A. Ask the team member to follow the approved communications management plan to communicate their issue B. Schedule a meeting with the concerned team member to review and update the issue log together C. Review the risk register with the team member to find the proper response action for this issue D. Ask the team member to raise a change request to assess the issue in detail Correct Answer: B This question is in PMP exam For getting PMP Certificate