A project manager works for an organization that intends to begin using agile delivery, but there is a lack of support from some business units. The project manager needs to address the lack of trust in agile. What should the project manager recommend?

QuestionsCategory: PMPA project manager works for an organization that intends to begin using agile delivery, but there is a lack of support from some business units. The project manager needs to address the lack of trust in agile. What should the project manager recommend?
Admin Staff asked 11 months ago
A project manager works for an organization that intends to begin using agile delivery, but there is a lack of support from some business units.
The project manager needs to address the lack of trust in agile.
What should the project manager recommend?

A. Negotiate special arrangements for an agile pilot project.

B. define detailed work instructions for agile project delivery.

C. Implement and establish an agile framework for the project.

D. Hire a team of contractors for agile project delivery.










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.