A project manager writes to the receiving organization to inform them that all acceptance activities are completed with success and it's time to initiate handover. The receiving manager replies that the team will not be ready for the handover procedure for another two weeks. What should the project manager do? A. Issue an internal change request to secure the resources for an additional two weeks. B. Request that the receiving manager issue a change request to prolong the project by two weeks. C. Inform the project sponsor of the two-week delay and replan activities to minimize delays. D. Deliver to the receiving manager on time, who can then make a knowledge transfer to their team. Correct Answer: C This question is in PMP exam For getting PMP Certificate
Please login or Register to submit your answer