A project sponsor asked the product owner to deliver the functionality that provides the highest return on investment (ROI) as soon as possible. Which artifact should the project lead use to track benefits? A. Requirements backlog B. Product backlog C. Project charter D. Project scope Correct Answer: B This question is in PMP exam For getting PMP Certificate