A project sponsor receives project information and updates in a timely manner, but the sponsor is concerned because key information is missing in the reports. What should the project manager do? A. confirm that the project information is understood and feedback is received. B. Determine communication methods, frequency, and level of detail. C. Review the communication needs of key stakeholders. D. Provide all project information to the stakeholder. Correct Answer: C This question is in PMP exam For getting PMP Certificate