A project team has recently completed the initial sprint for developing an automated payroll system for a company. The project manager has scheduled a sprint planning meeting with the product owner and team members to discuss which features should be worked on next. Which two pieces of information does the project manager need in order to make this meeting productive and effective? (Choose two.) A. Company mission and vision B. Sprint goal C. Sprint charter D. Product backlog E. Burndown chart Correct Answer: BD This question is in PMP exam For getting PMP Certificate