A project team has run into an issue with a vendor who is known for a lack of quality. The project manager must ensure that the quality problem is addressed appropriately. What should the project manager do to start the issue resolution process?

QuestionsCategory: PMPA project team has run into an issue with a vendor who is known for a lack of quality. The project manager must ensure that the quality problem is addressed appropriately. What should the project manager do to start the issue resolution process?
Admin Staff asked 1 year ago
A project team has run into an issue with a vendor who is known for a lack of quality. The project manager must ensure that the quality problem is addressed appropriately.
What should the project manager do to start the issue resolution process?

A. Meet with the vendor and request corrective actions.

B. Engage the test team to improve the quality.

C. Review the risk register and follow the response strategy.

D. Update the risk register and document any corrective actions.










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.