A project team is completing a design, while another team in a different country is performing implementation. How should the project manager communicate the design to the implementation team? A. Upload the design documents into the project repository. B. Conduct a workshop with all of the stakeholders. C. Send a detailed email with the completed design document. D. Conduct a workshop with both of the teams. Correct Answer: D This question is in PMP exam For getting PMP Certificate