A project team is in the planning stage and has prepared a list of activities and completed sequencing the activities. During a review, the team noted that there is a dependency missing between: · Test the product · Release to customer According to the quality management plan, the product must be tested before being released. How should the project manager enter this dependency? A. Start to start B. Finish to start C. Finish to nish D. Start to nish Correct Answer: B This question is in PMP exam For getting PMP Certificate