A project team is using one of the visual management tools to identify dependencies. It was identified that domain knowledge from one team needs to be shared with another team to ensure the continuity of deliverables. What should the project manager do? A. Remove the dependency to eliminate the need for knowledge sharing. B. Redistribute the team members so knowledge is available in both teams. C. Merge both teams into one team so the knowledge is commonly available. D. Request the respective teams to plan for knowledge-sharing sessions. Correct Answer: D This question is in PMP exam For getting PMP Certificate