A project team is using one of the visual management tools to identify dependencies. It was identified that domain knowledge from one team needs to be shared with another team to ensure the continuity of deliverables. What should the project manager do?

QuestionsCategory: PMPA project team is using one of the visual management tools to identify dependencies. It was identified that domain knowledge from one team needs to be shared with another team to ensure the continuity of deliverables. What should the project manager do?
Admin Staff asked 1 year ago
A project team is using one of the visual management tools to identify dependencies. It was identified that domain knowledge from one team needs to be shared with another team to ensure the continuity of deliverables.
What should the project manager do?

A. Remove the dependency to eliminate the need for knowledge sharing.

B. Redistribute the team members so knowledge is available in both teams.

C. Merge both teams into one team so the knowledge is commonly available.

D. Request the respective teams to plan for knowledge-sharing sessions.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.