A project team member identified a defect in the initial solution design for a project. The stakeholders are not sure whether to deploy the system or not. What should the project manager do? A. Propose a solution redesign for the project. B. Revise the project's quality control measurements. C. Perform risk analysis against the issue. D. Develop a mitigation based on the solution design. Correct Answer: C This question is in PMP exam For getting PMP Certificate