A senior management team member contacts an agile project lead and mentions that certain features the senior manager thought would be in the current release were not included. What should the agile project lead do? A. Send the product roadmap to the senior manager. B. Assure the senior manager that these features will be queued up in the next sprint. C. Invite the senior manager to the next planning meeting. D. Meet with the team to understand why the senior manager's features were not included. Correct Answer: D This question is in PMP exam For getting PMP Certificate