A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance. What should the senior project manager do now? A. Send a gentle reminder to the technical service team. B. Use interpersonal skills to expedite the issue. C. Update the issue log with the status and priority. D. Issue a formal warning to the technical service team. Correct Answer: C This question is in PMP exam For getting PMP Certificate