A sponsor requires that the established quality standards for the project be met. As a result, the sponsor asks the project manager for stable measures to ensure that the quality is met. Which three actions should the project manager do? (Choose three.)

QuestionsCategory: PMPA sponsor requires that the established quality standards for the project be met. As a result, the sponsor asks the project manager for stable measures to ensure that the quality is met. Which three actions should the project manager do? (Choose three.)
Admin Staff asked 1 year ago
A sponsor requires that the established quality standards for the project be met. As a result, the sponsor asks the project manager for stable measures to ensure that the quality is met.
Which three actions should the project manager do? (Choose three.)

A. Identify in the iteration planning the acceptance criteria that meet quality standards.

B. Identify the acceptance criteria during the retrospective that meet the quality standards.

C. Analyze the lessons learned to determine appropriate testing metrics in quality standards.

D. Incorporate performance metrics on the verified deliverables according to quality standards.

E. Perform a risk analysis to determine the impact of not complying with quality standards.








Correct Answer: ACD

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.