A stakeholder informs the project manager about a few compliance-related gaps and issues. The stakeholder then presents several suggestions to the project manager to address the issues. What should the project manager do? A. Discuss the suggestions with the staff responsible for the compliance issues. B. Review this with the project sponsor to avoid compliance gaps and issues. C. Log the feedback from the compliance gaps in the lessons learned register. D. Use the compliance issues to identify coaching and mentoring opportunities. Correct Answer: A This question is in PMP exam For getting PMP Certificate