A stakeholder informs the project manager about a few compliance-related gaps and issues. The stakeholder then presents several suggestions to the project manager to address the issues. What should the project manager do?

QuestionsCategory: PMPA stakeholder informs the project manager about a few compliance-related gaps and issues. The stakeholder then presents several suggestions to the project manager to address the issues. What should the project manager do?
Admin Staff asked 1 year ago
A stakeholder informs the project manager about a few compliance-related gaps and issues. The stakeholder then presents several suggestions to the project manager to address the issues.
What should the project manager do?

A. Discuss the suggestions with the staff responsible for the compliance issues.

B. Review this with the project sponsor to avoid compliance gaps and issues.

C. Log the feedback from the compliance gaps in the lessons learned register.

D. Use the compliance issues to identify coaching and mentoring opportunities.










Correct Answer: A

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.