A steering committee member is complaining about the weekly report. They stated that the report is too long and has unnecessary details. As a result, they are unable to obtain the main message and take action. What should the project manager do to avoid similar complaints? A. Send a shorter daily report to this steering committee member. B. Demonstrate the weekly reports in a presentation for the steering committee member. C. Verify the information needed for steering committee members. D. Present the status at a weekly meeting with the steering committee. Correct Answer: C This question is in PMP exam For getting PMP Certificate