A struggling company is executing a critical project. However, due to external environment changes, there is not enough funding to complete the project. What should the project manager do first? A. Reduce the scope of the project to match the available funds. B. Park the project until the external environment is favorable. C. Ask the project sponsor to look for additional funding. D. Assess the impact and evaluate alternatives to accommodate the change. Correct Answer: D This question is in PMP exam For getting PMP Certificate