A struggling company is executing a critical project. However, due to external environment changes, there is not enough funding to complete the project. What should the project manager do first?

QuestionsCategory: PMPA struggling company is executing a critical project. However, due to external environment changes, there is not enough funding to complete the project. What should the project manager do first?
Admin Staff asked 1 year ago
A struggling company is executing a critical project. However, due to external environment changes, there is not enough funding to complete the project.
What should the project manager do first?

A. Reduce the scope of the project to match the available funds.

B. Park the project until the external environment is favorable.

C. Ask the project sponsor to look for additional funding.

D. Assess the impact and evaluate alternatives to accommodate the change.










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.