A team has noticed a labeling mistake in two different prototypes. The mistake resulted in a need to apply a different destructive testing plan for each prototype. This resulted in a decline in team morale. What should the project lead do? A. Lead the team through the next sprint to prevent a similar issue. B. In uence stakeholders to support the team allowing recovery within limits. C. Bring in subject matter experts (SMEs) to coach the team. D. Use cost and time contingencies to mitigate a project baseline impact. Correct Answer: B This question is in PMP exam For getting PMP Certificate