A team is about to close a deployment and is waiting to receive critical information from the customer. The customer continues to postpone sending information, which is consequently delaying the deployment. What should the project manager have done to prevent the delay? A. Delegated the task to the product owner B. Asked the team to use the sample data C. Engaged the sponsor and sought their support D. Received all key information ahead of time Correct Answer: D This question is in PMP exam For getting PMP Certificate
Please login or Register to submit your answer