A team is not delivering the committed work. Cards are not moving on the kanban board, and the burndown chart shows that the sprint progress is slow. What should the agile project manager do? A. Consider the use of alternative performance metrics. B. Change the work in progress (WIP) limit to re ect the team's capacity. C. Discuss the performance with senior leadership. D. Meet with the project team members who are slow in delivering tasks. Correct Answer: D This question is in PMP exam For getting PMP Certificate