A team realizes that there is no access to data that the project depends on to complete the current iteration. This dependency was known; however, the team is unsure of the available options to remove this obstacle. What should the project manager do next? A. Move the dependent task to the next iteration. B. Guide the team to determine alternatives. C. Escalate the issue to the company's IT manager. D. Escalate the issue to the project sponsor. Correct Answer: B This question is in PMP exam For getting PMP Certificate