A technical manager newly appointed by the client, visits the project site to verify the project deliverables. The technical manager feels that the project manager has not been providing enough information. What should the project manager do first to resolve this situation?

QuestionsCategory: PMPA technical manager newly appointed by the client, visits the project site to verify the project deliverables. The technical manager feels that the project manager has not been providing enough information. What should the project manager do first to resolve this situation?
Admin Staff asked 1 year ago
A technical manager newly appointed by the client, visits the project site to verify the project deliverables. The technical manager feels that the project manager has not been providing enough information.
What should the project manager do first to resolve this situation?

A. Update the issue log and escalate to the project sponsor

B. Identify the lack of information as a risk and update the risk register

C. Schedule more frequent meetings with the technical manager

D. Review and update the stakeholder engagement plan










Correct Answer: D

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.