A technician needs to update the network firewall, which will cause a temporary outage. The technician submits a change management request to perform the required maintenance. Which of the following provides details about what the technician will need to do if the update fails? A. Back-out plan B. Scope of the change C. Risk analysis D. End-user acceptance  Suggested Answer: C Community Answer: A This question is in 220-1002: CompTIA A+ Certification Exam: Core 2 For getting CompTIA A+ Certificate Disclaimers: The website is not related to, affiliated with, endorsed or authorized by CompTIA. Trademarks, certification & product names are used for reference only and belong to CompTIA. The website does not contain actual questions and answers from CompTIA's Certification Exams.