A verbal announcement is made that the new team member joining the Scrum team has limited mobility. The scrum master is aware that some team members are unsure how the dynamics of the team will change. What should the scrum master do? A. Create a stakeholder engagement plan B. Design a communications management plan C. Update the team charter accordingly D. Set up a meeting to discuss accommodations the team will have to make Correct Answer: D This question is in PMP exam For getting PMP Certificate