A virtual team has disagreements about the client’s requirements. Although the requirements are written, the language seems ambiguous for some of the team members who are working abroad. The local team members argue that the language is clear, but that there is a lack of competence from the international team members. Which two actions should the project manager take? (Choose two.)

QuestionsCategory: PMPA virtual team has disagreements about the client’s requirements. Although the requirements are written, the language seems ambiguous for some of the team members who are working abroad. The local team members argue that the language is clear, but that there is a lack of competence from the international team members. Which two actions should the project manager take? (Choose two.)
Admin Staff asked 1 year ago
A virtual team has disagreements about the client's requirements. Although the requirements are written, the language seems ambiguous for some of the team members who are working abroad. The local team members argue that the language is clear, but that there is a lack of competence from the international team members.
Which two actions should the project manager take? (Choose two.)

A. Assign projects with local clients to the local project team members.

B. Train all project team members to recognize and discuss cultural differences

C. Ensure that local team members explain the requirements to the international team members

D. Provide training to international team members to ensure their understanding of the requirements.

E. Address the language ambiguity in the requirements to ensure all team members understand them








Correct Answer: CD

This question is in PMP exam
For getting PMP Certificate


Next Post

Recommended

Welcome Back!

Login to your account below

Create New Account!

Fill the forms below to register

Retrieve your password

Please enter your username or email address to reset your password.